Reply To: Fake Schedules

Home Forums Q & A Board Fake Schedules Reply To: Fake Schedules

#1918
Anonymous
Inactive

First, a good check of the logic should be done to ensure that no critical logic is missing, especially relationships related to logistics. Logistical scheduling relationships are often overlooked or disregarded. Never blindly increase durations for the sake of using up schedule float. Often, critical relationships were missed. Punchout is often scheduled optimistically.